Excavation for the pump room footers was completed on April 11th. Concrete was poured on April 13th. Footer excavation for the lifeguard room occurred the week of April 18th. The plumbing contractor will be starting the sanitary sewer construction the week of April 25th.
Any questions about this project will be answered by calling 412-884-0505.