Update on road and utility projects along the Provost and Weyman corridors…
PROVOST ROAD: The Columbia Gas contractor continues to experience delays with the pipeline replacement project. The delays are caused by aging infrastructure and incomplete utility mapping of the area. The contractor hopes to have Provost Road open by the first week of July.
WEYMAN BRIDGE PROJECT: PennDOT plans to begin the Weyman Road bridge replacement project in July. Weyman Road is tentatively scheduled to close between Red Dot Storage and Marathon Gas on July 10, 2023 and will remain closed through November 2023.
We will continue to provide updates as more information becomes available.