Weyman Road is schedule to reopen at the end of December. Final asphalt work will occur in Spring 2024.
Baptist Road Water Line Replacement Project has reached the half way point. Contractor estimates the project will continue for another 4 weeks. Work hours remain 7:00 pm-5:00 am Monday through Thursday.